Actual Start Date (AS)

Effective Project Management depends largely on keeping track of Actual Start Dates to determine productivity. The Actual Start Date marks the beginning of work on a scheduled activity, instead of the date that the project was accepted or assigned. By determining the length of time between the Actual Start Date and the completion of the project, Project Management can determine the output of workers. Actual Start Date and the assignment date of the project may coincide, but the date of assignment does not imply that work began on the project at that point in time. It is therefore imperative that the Actual Start Date be accurately communicated to Project Management, especially at the completion of the assignment. All scheduled activities have Actual Start Dates, and must always be recorded: in the eventStart Date differs fr that an Actual om the expected start of a project, both dates and, if necessary, times must be noted for Project Management. Falsifying Actual Start Dates not only threatens the usefulness of this measurement and creates inconsistencies in data for Project Management, but may result in disciplinary action.

This term is defined in the 3rd edition of the PMBOK but not in the 4th.

Related Posts

  1. Start Date

    A start date of a project is sometimes determined by the expected completion date. If a project is to be completed on a certain date and the project takes 90 days, then prior to the 90th day scheduled for completion, project management will determine the start date as to when everything will get underway. There [...]

  2. Scheduled Start Date (SS)

    The Scheduled Start Date (SS), also called the Planned Start Date, is the planned beginning of work on an assignment. Project Management will normally assign a start date for scheduled activities. The Scheduled Start Date is bounded by the early start date, when work on a project begins before the scheduled start date, and the [...]

  3. Baseline Start Date

    The term baseline start date applies to the actual scheduled start date of a schedule activity within the approved schedule baseline. The baseline start date will typically be estimated at the onset of a schedule activity based on a determination of how much work needs to be done, how many team members will be required [...]

  4. Actual Finish Date (AF)

    Project management must always keep in mind the predicted completion of the task. Once the work has ended, the project has reached its actual finish date (AF). This can be different from when the job is ruled as “finished”. That is due to the incidence of certain tasks being labeled as “finished” when a large [...]

  5. Planned Start Date

    See scheduled start This term is defined in the 3rd edition of the PMBOK but not in the 4th.

Leave a Comment