• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar

Project Management Knowledge

Simply explained by a PMI-certified Project Manager

  • Home
  • Acronyms and Abbreviations
  • Definitions
  • About the Author
  • Deutsch
  • Show Search
Hide Search
You are here: Home / Definitions / S / Start-to-Finish (SF)

Start-to-Finish (SF)

Those in project management must be certain to keep a logical flow to their projects. In this case, a successor task cannot start until the predecessor task has started, and this is implemented  in a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be able to communicate the proper start-to-finish (SF) order for activities in the project to their employees. This will create more efficient work and facilitate the completion of the overall project.

Careful planning of a project can avoid wasted time. While the employees might not be aware of which activities are called the successors and which are the predecessors, those in project management must know. A consciousness of successor and predecessor tasks will facilitate the formulation of a start-to-finish (SF) plan for the completion of the project. The only aspect of this plan which the workers should know is that the predecessor activity has to begin before its successor task can be completed. Those in project management can easily convey this start-to-finish (SF) plan by communicating to their employees an ordered list of tasks to accomplish for the completion of the larger project.

This term is defined in the 3rd and the 4th edition of the PMBOK.

Related Articles:

 
  • Acceptance – Definition Acceptance is the noun form of the previously defined verb “accept“. It represents the state of being in which one...
  •  
  • PMBOK, 4th edition The PMI has released the 4th edition of the Project Management Body of Knowledge, and while the members only-PDF cannot...
  •  
  • Summary Activity, Hammock Activity A project can be broken down into segments with each subproject being used to develop a subnetwork diagram of activities....
  •  
  • Finish-to-Start The term finish to start refers specifically to the logical relationship that exits between the activities that make up he...
  •  
  • Guideline Guidelines are very important in project management. A guideline is an important official recommendation indicating different policies, procedures or standard...
  • Primary Sidebar

    Articles

    • November 2023
    • September 2023
    • August 2023
    • July 2023
    • June 2023
    • May 2023
    • April 2023
    • March 2023
    • February 2023
    • January 2023
    • December 2022
    • August 2021
    • September 2020
    • October 2019
    • October 2018
    • April 2017
    • June 2016
    • April 2016
    • November 2015
    • April 2013
    • March 2013
    • May 2011
    • April 2011
    • March 2011
    • February 2011
    • January 2011
    • December 2010
    • November 2010
    • October 2010
    • September 2010
    • August 2010
    • July 2010
    • March 2010
    • January 2010
    • October 2009
    • August 2009
    • June 2009
    • April 2009
    • March 2009
    • February 2009
    • January 2009
    • December 2008
    • November 2008
    • October 2008
    • September 2008
    • August 2008
    • July 2008
    • June 2008
    • January 2008

    Dear Visitor,

    I am a certified project manager (PMP) - Please let me know if you have any questions about project management that are not explained on this site!

    Best Regards,

    Tom

    Copyright © 2023

    • Privacy Policy