What PMBOK 8 Did to Cost Management: Three New Process Names

PMBOK® Guide 6 had four cost processes. PMBOK® Guide – Eighth Edition also has four, but three of them carry different names, and they no longer sit in a knowledge area called Project Cost Management. If you still search for “Plan Cost Management”, “Determine Budget” or “Control Costs”, you are looking for names the current guide does not use. This article lines up the old and the new names and shows what the definitions actually change.

Old and new names side by side

PMBOK 6 (Project Cost Management, chapter 7)PMBOK 8 (Finance performance domain, section 2.4.2)
7.1 Plan Cost Management2.4.2.1 Plan Financial Management
7.2 Estimate Costs2.4.2.2 Estimate Costs
7.3 Determine Budget2.4.2.3 Develop Budget
7.4 Control Costs2.4.2.4 Monitor and Control Finances

We searched the full text of PMBOK 8 for the old names; the PMBOK 6 names come from its chapter 7. “Plan Cost Management” and “Determine Budget” have zero hits in PMBOK 8. “Control Costs” appears only as an ordinary verb phrase in running text, never as a process name. Only “Estimate Costs” survives unchanged.

What changed beyond the names

Plan Financial Management is defined as the process of defining how project revenues and expenses will be estimated, budgeted, managed, monitored and controlled. The word “revenues” is the difference: PMBOK 6 planned how costs would be handled, PMBOK 8 plans how money in both directions will be handled. The outputs shown in Figure 2-27 are the financial management plan and a funding strategy. The process is performed once up front or at predefined points in the project. See also our entry on Plan Cost Management, the PMBOK 6 predecessor.

Estimate Costs keeps its name and its definition: developing an approximation of the cost of resources needed to complete project work. PMBOK 8 says it is performed periodically as needed. Our page on Estimate Costs covers the technique.

Develop Budget aggregates the estimated costs of individual activities or work packages to establish an authorized cost baseline. That is the same job as Determine Budget in PMBOK 6, under a new verb. Figure 2-29 lists the cost baseline and project funding requirements as outputs, and cost aggregation, reserve analysis, funding limit reconciliation and financing among the tools. For the old term, see Determine Budget.

Monitor and Control Finances is where the scope grows most. The guide describes it as tracking expenditures, updating financial records, adjusting the cost baseline and the revenue forecasts, implementing corrective actions for financial risks, and doing variance analysis against planned costs. Its stated aim is that the project stays financially viable. It runs throughout the project. The PMBOK 6 predecessor is Control Costs.

Why this matters for searching and studying

Most material online, including older pages on this site, still uses the PMBOK 6 vocabulary. If a course, a template or a colleague says “Determine Budget”, they mean what PMBOK 8 now calls Develop Budget. The same pattern appeared in the schedule area, where six processes became three, and in the glossary terms PMBOK 8 dropped. For the bigger picture of the edition, read our overview of PMBOK 8.

What we did not check

We compared process names, definitions and the figures for the four processes. We did not compare every input, tool and output line by line between the two editions, so do not read this article as a complete mapping of all inputs and outputs. PMI’s free table of contents may not list the process names, so the primary source for the details is the guide itself.

Sources: PMBOK® Guide – Eighth Edition, sections 2.4.2.1 to 2.4.2.4 and Figures 2-26 to 2-30 (pages 61 to 65); PMBOK® Guide – Sixth Edition, chapter 7; PMI PMBOK Guide page; PMBOK Guide Eighth Edition table of contents (PDF).