PMBOK 8 Resource Processes: From Six to Five

Titelbild: KI-generiert (Gemini)

PMBOK® Guide 6 had six resource processes in chapter 9. PMBOK® Guide – Eighth Edition has five. Two of the old team processes, Develop Team and Manage Team, are merged into one process called Lead the Team. If you look for “Develop Team”, “Manage Team” or “Control Resources” in the new guide, you will not find them as process names.

Old and new names side by side

PMBOK 6 (Project Resource Management, chapter 9)PMBOK 8 (Resources performance domain, section 2.6.2)
9.1 Plan Resource Management2.6.2.1 Plan Resource Management
9.2 Estimate Activity Resources2.6.2.2 Estimate Resources
9.3 Acquire Resources2.6.2.3 Acquire Resources
9.4 Develop Team2.6.2.4 Lead the Team
9.5 Manage Team
9.6 Control Resources2.6.2.5 Monitor and Control Resourcing

We searched the full text of PMBOK 8 for the old names. “Develop Team”, “Manage Team”, “Control Resources” and “Estimate Activity Resources” have zero hits. The PMBOK 6 names come from the table of contents of its chapter 9.

What changed beyond the names

Plan Resource Management keeps its name. PMBOK 8 defines it as defining how to estimate, acquire, lead and utilize physical, virtual or team resources. It lists the responsibility assignment matrix, organizational theory, green human resource management, the resource-based view and SWOT analysis as specific tools. Effective planning should consider the availability of, or competition for, scarce resources.

Estimate Resources replaces Estimate Activity Resources. The definition is still estimating team resources and the type and quantities of physical or virtual resources needed for the work. PMBOK 8 stresses the link to the Schedule performance domain.

Acquire Resources keeps its name. PMBOK 8 adds that the acquisition is based on the activity list.

Lead the Team replaces Develop Team and Manage Team. PMBOK 6 defined Develop Team as improving competencies, team member interaction and the team environment. It defined Manage Team as tracking performance, providing feedback, resolving issues and managing team changes. PMBOK 8 puts both into one definition and splits the content into management activities (processes, planning, coordinating, measuring) and leadership activities (influencing, motivating, listening, enabling). Team development and high-performing teams are now sub-sections of this process.

Monitor and Control Resourcing replaces Control Resources. Both ensure that assigned resources are available as planned and compare planned with actual use. PMBOK 8 limits the process to physical and virtual resources such as equipment, materials, facilities, software and licenses. Team members are covered by Lead the Team.

Why this matters for searching and studying

Most material online, including older pages on this site, still uses the PMBOK 6 vocabulary. A course that teaches “Develop Team” and “Manage Team” as separate processes teaches the 2017 structure. The same pattern appeared in the scope processes, the cost processes and the schedule area, where six processes became three. For the larger picture, read our overview of PMBOK 8.

What we did not check

We compared process names and the definitions in section 2.6.2. We did not compare inputs, tools and outputs line by line, so this is not a complete mapping. PMI’s free table of contents does not go down to the process level, so the primary source for the details is the guide itself.

Sources: PMBOK® Guide – Eighth Edition, section 2.6.2 (Resources performance domain, processes, from page 80); PMBOK® Guide – Sixth Edition, chapter 9; PMI PMBOK Guide page; PMBOK Guide Eighth Edition table of contents (PDF).

By Tom, PMP-certified since 2004. Last updated: October 2026