PMBOK 8 Risk Processes: Seven Become Six

Titelbild: KI-generiert (Gemini)

PMBOK® Guide 6 had seven risk processes in chapter 11. PMBOK® Guide – Eighth Edition has six. Perform Qualitative Risk Analysis and Perform Quantitative Risk Analysis are merged into one process called Perform Risk Analysis. If you look for the two old names in the new guide, you will not find them as process names.

Old and new names side by side

PMBOK 6 (Project Risk Management, chapter 11)PMBOK 8 (Risk performance domain, section 2.7.2)
11.1 Plan Risk Management2.7.2.1 Plan Risk Management
11.2 Identify Risks2.7.2.2 Identify Risks
11.3 Perform Qualitative Risk Analysis2.7.2.3 Perform Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses2.7.2.4 Plan Risk Responses
11.6 Implement Risk Responses2.7.2.5 Implement Risk Responses
11.7 Monitor Risks2.7.2.6 Monitor Risks

We searched the full text of PMBOK 8 for the old names. “Perform Qualitative Risk Analysis” and “Perform Quantitative Risk Analysis” have zero hits. The PMBOK 6 names come from the table of contents of its chapter 11.

What changed beyond the names

Perform Risk Analysis replaces Perform Qualitative Risk Analysis and Perform Quantitative Risk Analysis. PMBOK 6 defined the qualitative process as prioritizing individual project risks by assessing probability and impact, and the quantitative process as numerically analyzing the combined effect of individual risks and other sources of uncertainty on overall project objectives. PMBOK 8 describes one iterative process that combines both. Qualitative analysis is conducted throughout the project. Quantitative analysis may not be required for every project, but when it is used, it is also conducted throughout the project. PMBOK 6 already said that the quantitative process is not required for every project, so this part is unchanged.

Plan Risk Management keeps its name. PMBOK 8 defines it as defining how to conduct risk management activities for a project, to begin when the project is conceived and to be completed early in the project.

Identify Risks keeps its name. PMBOK 8 stresses that the process covers both negative and positive risks, that it separates genuine risks from nonrisks such as concerns and issues, and that identification is iterative because not all risks can be identified at the outset.

Plan Risk Responses, Implement Risk Responses and Monitor Risks keep their names. PMBOK 8 describes Plan Risk Responses as developing options, selecting strategies and agreeing on actions for overall project risk exposure and for individual risks. In PMBOK 8, Monitor Risks also includes planning responses for new risks and states that risk owners are assigned to maintain continuity. The PMBOK 6 definition mentions neither.

Why this matters for searching and studying

Most material online, including older pages on this site, still teaches qualitative and quantitative risk analysis as two separate processes, which is the 2017 structure. The same pattern appeared in the resource processes, the scope processes, the cost processes and the schedule area, where six processes became three. For the larger picture, read our overview of PMBOK 8.

What we did not check

We compared process names and the definitions in section 2.7.2. We did not compare inputs, tools and outputs line by line, so this is not a complete mapping. PMI’s free table of contents does not go down to the process level, so the primary source for the details is the guide itself.

Sources: PMBOK® Guide – Eighth Edition, section 2.7.2 (Risk performance domain, processes, from page 95); PMBOK® Guide – Sixth Edition, chapter 11; PMI PMBOK Guide page; PMBOK Guide Eighth Edition table of contents (PDF).

By Tom, PMP-certified since 2004. Last updated: November 2026