Actual Finish Date (AF)

Project management must always keep in mind the predicted completion of the task. Once the work has ended, the project has reached its actual finish date (AF). This can be different from when the job is ruled as “finished”. That is due to the incidence of certain tasks being labeled as “finished” when a large majority of the work has been done, but the job still needs some work.
The actual finish date (AF) can differ from the projected completion date. Unanticipated events and other delays can contribute to that difference. Projects with environmental factors often have several days built into the time table to allow for weather related delays in the work. Project management can assist in bringing the predicted and actual finish date (AF) closer together by minimizing external forces and events which might slow work. Those working in project management might consider offering some incentive to their employees for completing the job with an earlier actual finish date than the predicted date. This can encourage faster, more efficient work among the employees who would like to get work done on the task as soon as possible for their own benefit and that of the company.

This term is defined in the 3rd edition of the PMBOK but not in the 4th.

Related Posts

  1. Target Finish Date

    Staying on task is essential in all that you do in everyday life. It serves as the cohesion to all of the success that will ever be assigned to you and appreciated by others. Looking through the proverbial scope of Project Management, it is certain that timely completion is most vital in all that is [...]

  2. Actual Start Date (AS)

    Effective Project Management depends largely on keeping track of Actual Start Dates to determine productivity. The Actual Start Date marks the beginning of work on a scheduled activity, instead of the date that the project was accepted or assigned. By determining the length of time between the Actual Start Date and the completion of the [...]

  3. Baseline Finish Date

    The term baseline finish date applies to the date on which a schedule activity is expected to be completed within the approved schedule baseline. The baseline finish date will typically be estimated at the onset of a schedule activity based on a determination of how much work needs to be done, how many team members [...]

  4. Early Finish Date

    The phrase early finish date (also known by the abbreviation EF) refers, on the critical path method, to the earliest possible point at which the as yet to be completed elements of a schedule activity (or, depending on the particular context, the entire project as a whole) may potentially be completed . The early finish [...]

  5. Current Finish Date

    The term current start date refers to the deliberate and calculated estimate of the specific point in time at which the activity and or schedule activities is expected to be completed. The term current finish date is somewhat ambiguous and more properly phrased and termed date at which the activity is currently expected to be [...]

Leave a Comment