Budget

The noun budget is one that is used by nearly every individual and corporation on a daily basis. It can be defined, generally, as a particular sum of money that has been allocated for a particular item, prupose, or event over a specific or fixed period of time. An example of the term “budget” defined in this sense would be “Our monthly budget for entertainment has gone from $200 to $500 following my recent raise.” It can also refer to the itemization of anticipated expenses during that given time period along with, in many cases, proposed methods of financing those expenses. An example of this usage could be “I began preparing a budget for the end-of-year party.” In terms of project management, the work budget has similar meaning. A budget represents an approved estimate for either the entire project or for a particular schedule activity or work structure breakdown component. Budgets can be modified with proper approval at any point throughout the process, however, it is typically ideal to adhere to the predetermined budget whenever possible.

This term is defined in the 3rd and the 4th edition of the PMBOK.

Related Posts

  1. Budget at Completion

    The phrase budget at completion (often referred to as BAC) refers to the sum of all budget values that have been previously established for the work to be performed on a project, or on components within a project such as a schedule activity or work breakdown structure component. The budget at completion also can be [...]

  2. Request for Information

    Requests for information exist in many areas of our society, and typically refer to the seeking out of information by individuals from larger organizations for any multitude of utilization means on their end. The most commonly used meaning of request for information is in the context of governmental requests for information in which in individual, [...]

  3. Estimate to Complete

    The estimate to complete is an input output mechanism that is used to determine y the project team and the project leaders what will be the expected or anticipated costs that are going to be needed to ultimately complete the entirety of the remainder of work on the project or on a particular phase of [...]

  4. Estimate at Completion

    The phrase estimate at completion, which can also be referred to by the three letter anagram EAC, is an input output device that is used to measure the expected total cost of a particular schedule activity, a work breakdown structure, or of the project as a whole, in cases where the scope of work that [...]

  5. Schedule Activity

    When attempting to budget the totality of time that is both available and necessary when it comes to the timing of the project and all of its components, often times it is important to do a careful analysis pf the concise and discreet scheduled components of work that are available to be performed over the [...]

{ 2 comments… read them below or add one }

Johnbosco February 24, 2010 at 2:07 am

Under what conditions would a project manager make changes to a baseline without any impact to project budget?

When would a project manager not allow changes to a baseline?

Tom February 24, 2010 at 2:20 pm

Changes to a baseline could be possible if the project manager makes use of Fast Tracking, provided this method has no impact on the budget (which should not be the case).

Whether a project manager is allowed to make changes to a baseline or not depends on the authority the project manager is given, e.g. with respect to shifting a budget.

Leave a Comment