• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar

Project Management Knowledge

Simply explained by a PMI-certified Project Manager

  • Home
  • Acronyms and Abbreviations
  • Definitions
  • About the Author
  • Deutsch
  • Show Search
Hide Search
You are here: Home / Definitions / A / Activity-on-Node

Activity-on-Node

Activity-on-node is a project management term that refers to a precedence diagramming method which uses boxes to denote schedule activities. These various boxes or “nodes” are connected from beginning to end with arrows to depict a logical progression of the dependencies between the schedule activities. Each node is coded with a letter or number that correlates to an activity on the project schedule.

Typically, an activity-on-node diagram will be designed to show which activities must be completed in order for other activities to commence. This is referred to as “finish-to-start” precedence – meaning one activity must be finished before the next one can start. In the diagram below, activities A and D must be done so that activity E can begin. It is also possible to create other variations of this type of diagram. For example, a “start-to-start” diagram is one in which a predecessor activity must simply be started rather than fully completed in order for the successor activity to be initiated.

An activity-on-node diagram can be used to provide a visual representation of the network logic of an entire project schedule. Or, it can be used for any smaller section of the schedule that lends itself to being represented as having a defined beginning and end. To keep the logic in the diagram simple, it may be most effective to include only critical path schedule activities. The planned start date of each node may also be listed in the diagram legend in accordance with the project management timeline.

This term is defined in the 3rd edition of the PMBOK, but not in the 4th.

Related Articles:

 
  • Acceptance – Definition Acceptance is the noun form of the previously defined verb “accept“. It represents the state of being in which one...
  •  
  • PMBOK, 4th edition The PMI has released the 4th edition of the Project Management Body of Knowledge, and while the members only-PDF cannot...
  •  
  • To-Complete Performance Index The To-Complete Performance Index (TCPI) is a tool in project management that is used to measure the cost performance required...
  •  
  • Practice In nearly all phases of life, and regardless of what task or activity that particular life phase may entail, it...
  •  
  • Activity Resource Estimating [Process] Activity resource estimating is a process in which the project team carefully compiles a thorough listing of the resources that...
  • Primary Sidebar

    Articles

    • August 2023
    • July 2023
    • June 2023
    • May 2023
    • April 2023
    • March 2023
    • February 2023
    • January 2023
    • December 2022
    • August 2021
    • September 2020
    • October 2019
    • October 2018
    • April 2017
    • June 2016
    • April 2016
    • November 2015
    • April 2013
    • March 2013
    • May 2011
    • April 2011
    • March 2011
    • February 2011
    • January 2011
    • December 2010
    • November 2010
    • October 2010
    • September 2010
    • August 2010
    • July 2010
    • March 2010
    • January 2010
    • October 2009
    • August 2009
    • June 2009
    • April 2009
    • March 2009
    • February 2009
    • January 2009
    • December 2008
    • November 2008
    • October 2008
    • September 2008
    • August 2008
    • July 2008
    • June 2008
    • January 2008

    Dear Visitor,

    I am a certified project manager (PMP) - Please let me know if you have any questions about project management that are not explained on this site!

    Best Regards,

    Tom

    Copyright © 2023

    • Privacy Policy