• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar

Project Management Knowledge

Simply explained by a PMI-certified Project Manager

  • Home
  • Acronyms and Abbreviations
  • Definitions
  • About the Author
  • Deutsch
  • Show Search
Hide Search
You are here: Home / Definitions / C / Cost Variance (CV)

Cost Variance (CV)

The term cost variance, also known by the abbreviation of CV, refers specifically to the true measurement of cost performance on a particular project. The cost variance represents the algebraic difference between the earned value of a project (also known by the abbreviation of EV), and the actual cost of the project (also known by the abbreviation AC). The equation to determine the cost variance would be broken down as follows: CV = EV minus AC. If the resulting value for the cost variance is a number greater than zero (or “positive value”), then it is considered to be a favorable cost variance condition. A value that is less than zero, or a resulting “negative” value, represents a cost variance that is considered less than favorable. Because the cost variance is so dependent on the earned value and the actual cost, in order to maintain a favorable cost variance, it is to the project team’s advantage to minimize actual costs to the extent possible.

This term is defined in the 3rd and the 4th edition of the PMBOK.

Related Articles:

 
  • Acceptance – Definition Acceptance is the noun form of the previously defined verb “accept“. It represents the state of being in which one...
  •  
  • PMBOK, 4th edition The PMI has released the 4th edition of the Project Management Body of Knowledge, and while the members only-PDF cannot...
  •  
  • Cost Cost refers to the monetary value or financial pricing of a specific project activity. This cost includes all anticipated expenditures...
  •  
  • Variance Analysis Within the realm of project management, the concept of variance analysis is a central one. Variance analysis is the means...
  •  
  • Scope Change In almost any successful project management endeavor it is conceivable that some change in scope might be necessary. Veering from...
  • Primary Sidebar

    Articles

    • November 2023
    • September 2023
    • August 2023
    • July 2023
    • June 2023
    • May 2023
    • April 2023
    • March 2023
    • February 2023
    • January 2023
    • December 2022
    • August 2021
    • September 2020
    • October 2019
    • October 2018
    • April 2017
    • June 2016
    • April 2016
    • November 2015
    • April 2013
    • March 2013
    • May 2011
    • April 2011
    • March 2011
    • February 2011
    • January 2011
    • December 2010
    • November 2010
    • October 2010
    • September 2010
    • August 2010
    • July 2010
    • March 2010
    • January 2010
    • October 2009
    • August 2009
    • June 2009
    • April 2009
    • March 2009
    • February 2009
    • January 2009
    • December 2008
    • November 2008
    • October 2008
    • September 2008
    • August 2008
    • July 2008
    • June 2008
    • January 2008

    Dear Visitor,

    I am a certified project manager (PMP) - Please let me know if you have any questions about project management that are not explained on this site!

    Best Regards,

    Tom

    Copyright © 2023

    • Privacy Policy