• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar

Project Management Knowledge

Simply explained by a PMI-certified Project Manager

  • Home
  • Acronyms and Abbreviations
  • Definitions
  • About the Author
  • Deutsch
  • Show Search
Hide Search
You are here: Home / Definitions / O / Original Duration (OD)

Original Duration (OD)

Original duration is one of the most critical elements of effective and comprehensive project management, as it is a truly valid representation of the length of time that it was originally assumed it would take from the onset to the conclusion of the project. To be more specific, in terms of the life cycle of the project, the original duration (also known by the two letter anagram OD) refers specifically to the activity duration that was assigned at the onset of activity only. This original duration is a static element, and is not a living mark. It is not in any way, shape, or form updated as the project advances and there are some very particular reasons why it is a good idea for it to not change. Primarily, it is helpful for it to remain in its original state because it allows the project manager and project management team to view it in comparison to the actual duration and to the remaining duration when making an assessment of the progress to date.

This term is defined in the 3rd edition of the PMBOK but not in the 4th.

Related Articles:

 
  • Acceptance – Definition Acceptance is the noun form of the previously defined verb “accept“. It represents the state of being in which one...
  •  
  • To-Complete Performance Index The To-Complete Performance Index (TCPI) is a tool in project management that is used to measure the cost performance required...
  •  
  • PMBOK, 4th edition The PMI has released the 4th edition of the Project Management Body of Knowledge, and while the members only-PDF cannot...
  •  
  • Critical Chain Method The phrase critical chain method refers to a specific project management technique in which a schedule network analysis is used...
  •  
  • Issue Log There are many project documents involved in project management.  Project documents are necessary because they provide the team with the...
  • Primary Sidebar

    Articles

    • November 2023
    • September 2023
    • August 2023
    • July 2023
    • June 2023
    • May 2023
    • April 2023
    • March 2023
    • February 2023
    • January 2023
    • December 2022
    • August 2021
    • September 2020
    • October 2019
    • October 2018
    • April 2017
    • June 2016
    • April 2016
    • November 2015
    • April 2013
    • March 2013
    • May 2011
    • April 2011
    • March 2011
    • February 2011
    • January 2011
    • December 2010
    • November 2010
    • October 2010
    • September 2010
    • August 2010
    • July 2010
    • March 2010
    • January 2010
    • October 2009
    • August 2009
    • June 2009
    • April 2009
    • March 2009
    • February 2009
    • January 2009
    • December 2008
    • November 2008
    • October 2008
    • September 2008
    • August 2008
    • July 2008
    • June 2008
    • January 2008

    Dear Visitor,

    I am a certified project manager (PMP) - Please let me know if you have any questions about project management that are not explained on this site!

    Best Regards,

    Tom

    Copyright © 2023

    • Privacy Policy