• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar

Project Management Knowledge

Simply explained by a PMI-certified Project Manager

  • Home
  • Acronyms and Abbreviations
  • Definitions
  • About the Author
  • Deutsch
  • Show Search
Hide Search
You are here: Home / Definitions / V / Variance

Variance

In the project management world, variance is a measurable change from a known standard or baseline. In other words, variance is the difference between what is expected and what is actually accomplished. This is a different definition of variance compared to statistics where variance is defined as the squared deviation from the mean! You need to understand what kind of variance is referred to since there is a huge difference between these two concepts of variance.

In project management, variance baseline is established by identifying the cost, schedule and scope. Scope defines all the work which needs to be done. The project management team creates a work-breakdown structure (WBS) which is a hierarchical view of all tasks to be accomplished. The cost and schedule is then identified according to the work-breakdown structure (WBS). The cost for each goal or task is estimated sometimes by using an average daily, hourly, monthly or yearly rate. The fixed costs are identified for each goal or task. In addition, the project management workers estimate how long in days or hours a goal or task is to be accomplished, Then they create a time-phased budget to quantify the performance cost.

After identifying the scope, schedule and cost, the project managers create a plan to manage variances from the triple constraints of scope, schedule and cost. A positive variance means the project is going on ahead of schedule or is under the cost. A negative variance means the project is late or over the cost.

Variance tracking is key to project management and needs a logical approach. The project mangers identify the variance thresholds and develop a plan in case it happens.

This term is defined in the 3rd and the 4th edition of the PMBOK.

Related Articles:

 
  • Acceptance – Definition Acceptance is the noun form of the previously defined verb “accept“. It represents the state of being in which one...
  •  
  • PMBOK, 4th edition The PMI has released the 4th edition of the Project Management Body of Knowledge, and while the members only-PDF cannot...
  •  
  • To-Complete Performance Index The To-Complete Performance Index (TCPI) is a tool in project management that is used to measure the cost performance required...
  •  
  • Cost-Reimbursable Contract A cost-reimbursable contract is a variant of a contract that involves making a payment from the buyer to the seller...
  •  
  • Verification Verification is a quality assurance process or technique applied by Project Management whereby an evaluation of a component, product or...
  • Primary Sidebar

    Articles

    • November 2023
    • September 2023
    • August 2023
    • July 2023
    • June 2023
    • May 2023
    • April 2023
    • March 2023
    • February 2023
    • January 2023
    • December 2022
    • August 2021
    • September 2020
    • October 2019
    • October 2018
    • April 2017
    • June 2016
    • April 2016
    • November 2015
    • April 2013
    • March 2013
    • May 2011
    • April 2011
    • March 2011
    • February 2011
    • January 2011
    • December 2010
    • November 2010
    • October 2010
    • September 2010
    • August 2010
    • July 2010
    • March 2010
    • January 2010
    • October 2009
    • August 2009
    • June 2009
    • April 2009
    • March 2009
    • February 2009
    • January 2009
    • December 2008
    • November 2008
    • October 2008
    • September 2008
    • August 2008
    • July 2008
    • June 2008
    • January 2008

    Dear Visitor,

    I am a certified project manager (PMP) - Please let me know if you have any questions about project management that are not explained on this site!

    Best Regards,

    Tom

    Copyright © 2023

    • Privacy Policy